Wisteria Drive Waterline Replacement Project
Under Construction
Contractor
Simonson Construction Services
Location
N Azalea Blvd to S Azalea Blvd
Project Highlights
1,750 feet of new 8” waterline
Includes 4,100 square yards of road resurfacing
Replacing 4 hydrants and adding a smart hydrant for remote monitoring
New service connections from waterline to curb boxes
Lead service checks conducted during reconnection
Project Updates
1-12-2026 Update
Final restoration, including seed and straw, is scheduled for completion in early spring.