Home / Projects / Frank Avenue Waterline Replacement Project
Frank Avenue Waterline Replacement Project
Under Construction
Contractor
Simonson Construction Services
Location
Snyder to Harold
Project Highlights
1,175 feet of new 8” waterline
Replacing 3 hydrants and adding a smart hydrant for remote monitoring
New service connections from waterline to curb boxes
Lead service checks conducted during reconnection
Project Updates
12-1-25 Update
Frank Ave is nearing completion, with one mainline abandonment scheduled for tomorrow, December 2nd. The remaining work includes installing the concrete curb and completing final restoration.