5th Street NW Waterline Replacement Project

Under Construction

Contractor

Simonson Construction Services

Location

W Hopocan to Creedmore Ave

Project Highlights

  • 775 feet of new 8” waterline
  • Replacing 2 hydrants and adding a smart hydrant for remote monitoring
  • New service connections from waterline to curb boxes
  • Lead service checks conducted during reconnection

Project Updates

12-1-25 Update

Work on 5th Street is currently underway, with sewer video inspection in progress. Boring for the main line is scheduled to begin on Monday, December 8th. All live taps have been completed and are ready for tie‑ins.