Stratford Street Waterline Replacement Project

Under Construction

Contractor

Kenmore Construction

Location

31st Street to the dead end

Project Highlights

  • Installing 3,900 feet of new 8” waterline
  • Replacing 10 hydrants with 15 for improved emergency access
  • New service connections from waterline to curb boxes
  • Lead service checks during reconnection to aid City identification
  • Automated flushing unit installed to maintain water quality
  • Smart hydrant added for remote flow and pressure monitoring

Project Updates

2-11-26 Update

The new 8″ HDPE water main has been installed from 31st to 25th St SW. The boring crew expects to complete the remaining pipe installation by Friday, February 13, 2026. Once the full main is in place, crews will begin tying in the side streets. Testing of the new water main and associated services will follow.