Wisteria Drive Waterline Replacement Project

Under Construction

Contractor

Simonson Construction Services

Location

N Azalea Blvd to S Azalea Blvd

Project Highlights

  • 1,750 feet of new 8” waterline
  • Includes 4,100 square yards of road resurfacing
  • Replacing 4 hydrants and adding a smart hydrant for remote monitoring
  • New service connections from waterline to curb boxes
  • Lead service checks conducted during reconnection

Project Updates

1-12-2026 Update

Final restoration, including seed and straw, is scheduled for completion in early spring.